9th Street Construction Update

9th Street-October 2018

Phase 1 of the 9th Street (Lynn Lane) widening project between Flight Safety and Houston (81st) St. is anticipated to wrap up at the end of October, with Phase 2 expected to begin the week of Nov. 5.


Phase 1 includes the section of 9th Street between Ft. Worth and Houston Streets. Phase 2 stretches between Dallas and Ft. Worth Streets.


Work that has been completed so far includes:

  • Storm sewer system installed to Ft. Worth on west side of road
  • Widening of 9th from Ft. Worth to Houston
  • Broken Arrow Public School driveways on 9th Street demolished and prepped for placement


Here is the schedule of remaining work on Phase I: 

  • Week of Oct. 15
    • Placement of curb and gutter between Houston and Ft. Worth
    • Placement of BA Public School drives (during fall break)
    • Installation of storm curb inlets and accessories
  • Week of Oct. 22
    • Installation of sidewalks between Houston and Ft. Worth
    • Installation of residential drives just north of Ft. Worth on west side of roadway
    • Associated dirt-work completion within this phase of work
    • Roadway widening subgrade final adjustment
  • Week of Oct. 29
    • Installation of asphalt for road widening
    • Striping of road widening south of Ft. Worth
    • Demo of Phase 1 traffic control and cleanup
  • Week of Nov. 5
    • Start Phase 2, between Dallas and Ft. Worth


Weather conditions and waterline relocations have caused the overall project to be delayed approximately 1.5 weeks. Weather permitting, the City hopes to complete the entire project in spring 2019. The project costs approximately $5.9 million and is funded through the 2011 and 2014 General Obligation Bonds approved by voters.

Facebook Twitter Google Plus Email

Other News in News

Visit BA

Download the VisitBA app

Posted on: November 7, 2018
City Council Highlights graphic

City Council Highlights

Posted on: August 24, 2016
ba motion thumb0

Broken Arrow in Motion

Posted on: June 26, 2017
2017 State of the City address

Watch the 2017 State of the City address

Posted on: December 19, 2017
Baseball_indian springs 300

Youth Sports an Economic Driver for BA

Posted on: August 25, 2017
mobile tech

AT&T Bringing 5G to Broken Arrow

Posted on: March 30, 2017
image of new water connection to Tulsa

City Council Approves New Utility Rates

Posted on: December 7, 2016